Trails Recreation Center: Facility Refresh
Updated: Tuesday, April 14, 2026
Table of Contents
Project Overview
Big improvements are coming to Village Park in the summer of 2026! This exciting project will bring new amenities and important upgrades designed to better serve children, families, and the community as a whole. From new play opportunities to improved accessibility and site enhancements, these updates will help make Village Park an even more welcoming and enjoyable space for everyone.
One of the biggest highlights of the 2026 Improvement Project is a new play structure designed for children ages 2-5. This new area will include inclusive musical and sensory play features, creating more opportunities for imaginative play and interactive experiences for young visitors of all abilities. The project will also include a new restroom facility, which will be maintained weekly by staff to help keep the park clean, comfortable, and convenient for guests.
In addition to these new features, the Village Park: 2026 Improvement Project will include landscape, accessibility, and drainage improvements throughout the park. These upgrades are intended to improve both the function and appearance of the space while supporting long-term use and care. This project is made possible with additional funds from the City of Centennial, and we are grateful for their partnership in helping to bring these improvements to life.
Construction for Phase One of the Trails Recreation Center: Facility Refresh will run from October 2025 through February 2026.
Construction for Phase Two of the Trails Recreation Center: Facility Refresh is scheduled to run from February through June 2026. We will continue to add monthly construction updates below so community members can stay informed on progress, milestones, and what to expect during each phase of the project.
Trails Recreation Center: Facility Refresh Timeline
September 2025 - Project Announcement
September 2025 - Project Announcement
In September 2025, Trails Park and Recreation District announced its plans for a full facility refresh at the Trails Recreation Center. This multi-year project will include features like:
- New furniture in the rec center lobby
- Two new staff offices
- A brand new rentable conference room
- New teaching kitchen in the Gold Rush Room
- Updates to our community event rooms, like Conestoga and Gold Rush
- Improvements to our fitness/dance studios, like Wagon Wheel, Aerobics Room, and Cycling Room.
- Improved lighting, new vanities, partitions, and modern finishes in our locker rooms and restrooms
- New paint throughout the entire facility
- A refreshed childcare space with improved finishes and storage to better serve families.
Phase 1 — Trails Recreation Center: Facility Refresh Timeline
October 2025: Demolition Begins
October 2025: Demolition Begins
Construction crews completed several major demolition tasks to prepare the space for the next phase of work. This included removing the game room to make way for a new community conference room, remodeling the bathrooms and existing conference room, and demolishing hallway flooring in anticipation of updated finishes.
With demolition now complete, crews have moved into the framing stage. New walls, offices, and windows are beginning to take shape, marking an exciting first step in bringing the newly designed interior spaces to life.
November 2025: Taking Shape
November 2025: Taking Shape
In November, the TRC Refresh project made visible progress as construction moved from demolition into reconstruction. Crews completed major framing work throughout the renovated areas, helping define the layout of the updated spaces and bringing the new design to life. Painting also got underway, adding a fresh look and giving a clearer sense of how the finished interiors will come together. At the same time, electrical installation progressed throughout the project area, supporting the next phases of construction and helping prepare the renovated spaces for future use.
December 2025: Electric Spaces
December 2025: Electric Spaces
Crews completed painting throughout the corridors, offices, and remodeled spaces, giving the updated layout a bright, cohesive look. New flooring, carpet, and doors were also installed, improving comfort, acoustics, and the overall flow of the renovated areas.
At the same time, electrical work was finalized and updated lighting fixtures were put in place, helping create a modern, energy-efficient atmosphere throughout the space. With these major interior elements now complete, the project is entering its final phase and setting the stage for furniture installation, final touch-ups, and a planned reopening by the end of January.
January 2026: Phase 1 Complete
January 2026: Phase 1 Complete
Phase 1 of the Trails Recreation Center Facility Refresh project is complete! Learn more about the recent restroom upgrades, get the details on our new rentable conference room, and take a look at photos of the two new offices created for our growing Trails team.
Phase 2 — Trails Recreation Center: Facility Refresh Timeline
February 2026: Demolition and Early Progress
February 2026: Demolition and Early Progress
Visible improvements also started to take shape during February. In the Conestoga Room, the ceiling grid was painted white to brighten the space, while both rooms were patched, prepped, and painted. New ceiling tiles were installed in the Gold Rush and Conestoga Rooms, giving the spaces a cleaner, more updated look. Flooring preparation also began in the Conestoga Room, marking another important step toward the finished refresh.
March 2026: Finishes and Fixtures Take Shape
March 2026: Finishes and Fixtures Take Shape
Additional progress was also made on the Gold Rush kitchen glass door system with new header and track pieces installed. In the Conestoga Room, cabinets and sinks were delivered and installed, helping the space look more complete and adding useful storage and functionality. Plumbing work was also finished to connect the new sinks, bringing the room one step closer to being ready for use.
April 2026: Conestoga Reopens, Gold Rush Nears Completion
April 2026: Conestoga Reopens, Gold Rush Nears Completion
The biggest highlight in April was the reopening of the Conestoga Room, which is now back in service and available for community use. While a few minor punch list items still remain, including the wall partition replacement and updated lighting, the room is once again functional and serving the public. At the same time, steady progress continued in the Gold Rush Room, where kitchen cabinets and flooring were installed, stackable folding glass walls were added, and restoration of the room divider moved forward.
Looking ahead, several final touches are still planned for the Gold Rush Room, including carpet installation, kitchen appliances, countertops, and a hanging display mirror. With these remaining items on schedule, the Gold Rush Room is expected to be completed by June 1. Overall, April marked another important step forward in the facility refresh project, with visible progress bringing both spaces closer to full completion.
Updates and Information
We will continue to provide updates on social media and our website regarding the Trails Recreation Center: Facility Refresh and the construction process.
Please note that the design concepts presented are subject to change based on construction costs and design needs.