Tall Grass Park: 2026 Improvement Project (May Update)
Published: Tuesday, June 9, 2026
After years of planning, community feedback, and behind-the-scenes coordination, construction at Tall Grass Park is officially underway! May marked the first month of active work on site, and while things are just getting started, it’s exciting to see the project transition from planning into action.
Construction Gets Underway
Crews mobilized at Tall Grass Park in May, with safety fencing installed and site surveying completed to set the stage for construction. These early steps are an essential part of any project, helping ensure the work ahead is organized, safe, and aligned with the approved plans.
Earthwork Begins for Pickleball Courts
With the site secured, crews have begun earthwork in preparation for the two new pickleball courts — one of the most anticipated additions coming to the park. This grading and site prep work is the necessary first step before court construction can begin, and it reflects the momentum the project is building as it heads into the summer construction season.
We’ll continue to share monthly updates here as the project progresses through Summer and into Winter 2026. Thank you for your patience as construction gets underway; we’re looking forward to bringing these new amenities to the community!
For the full project background and timeline, visit the Tall Grass Park: 2026 Improvement Project page.
For the full project background and timeline, visit the Tall Grass Park: 2026 Improvement Project page. This project is made possible with funds from Arapahoe County Open Space.