The Tall Grass Park Improvement Project kept up its momentum in August, with several key milestones completed and an exciting date now on the calendar for pickleball court construction.
Site Grading Complete
Crews finished site grading throughout the park in August, an important step that prepares the ground for the remaining hardscape and court work ahead.
Boardwalk and Sidewalk Connection Finished
The boardwalk is fully finished, and crews also completed the concrete pour for the sidewalk connection, linking the new pathway into the rest of the park. Together, these improvements mark significant progress toward a more connected and accessible Tall Grass Park.
What's Next: Pickleball Court Pour Scheduled for September 2–3
With site prep well underway, Renner is now preparing for the pickleball court pour, scheduled for September 2–3. This marks a major milestone for the project, bringing the two new courts one step closer to completion.
We’ll continue to share monthly updates here as the project progresses through the rest of 2026. Thank you for your patience as construction continues; we’re looking forward to bringing these new amenities to the community!
For the full project background and timeline, visit the Tall Grass Park: 2026 Improvement Project page.
This project is made possible with funds from Arapahoe County Open Space.