Behind the Build: January 2004

January 2004 Wood roof trusses have been placed above the Climbing Wall area. The running track structural steel and decking is in progress

Behind the Build January 2004 Read More! Behind the Build: January 2004 Welcome back to Behind the Build as we kick off 2004 with a flurry of construction activity! Our […]

Behind the Build: December 2003

December 2003 Construction Pictures: Concrete slab pour in progress

Behind the Build December 2003 Read More! Behind the Build: December 2003 Welcome back to Behind the Build, where we continue our journey through the construction of the Trails Recreation […]

Behind the Build: November 2003

November 2003 Construction Pictures: metal roof deck and stud installation

Behind the Build November 2003 Read More! Behind the Build: November 2003 Welcome back to Behind the Build, where we celebrate the construction of the Trails Recreation Center month by […]

Behind the Build: October 2003

October 2003 Construction Pictures: masonry screen wall foundations being poured

Behind the Build October 2003 Read More! Behind the Build: October 2003 Welcome back to Behind the Build, where we continue our month-by-month celebration of the Trails Recreation Center’s 20th […]

Behind the Build: September 2003

September 2003 Construction Pictures: foundation forming and rebar placement

Behind the Build September 2003 Read More! Behind the Build: September 2003 Welcome back to Behind the Build, our monthly series celebrating the 20th anniversary of the Trails Recreation Center! […]

Behind the Build: August 2003

August 2003: Concrete truck pumping the trails recreation center foundation

Behind the Build August 2003 Read More! Behind the Build: August 2003 Welcome to the first post in our Behind the Build series, where we celebrate the 20th anniversary of […]