Search
Close this search box.

Behind the Build

August 2004

Behind the Build: August 2004

As we move through August, the transformation of the Trails Recreation Center is truly taking shape! This month has been filled with exciting advancements as we focus on the finer details that will make our facility a welcoming and functional space for the community. Let’s explore the highlights of this month’s construction progress!

Landscaping: Beautifying Our Surroundings

August marked significant progress in our landscaping efforts. Fine grading for landscape work and detention ponds has been completed, and the installation of the landscaping irrigation system is well underway. The layout for tree planting has also begun, ensuring a beautiful environment around the leisure pool and throughout the facility.

Interior Finishes: Creating a Welcoming Atmosphere

Inside the center, caulking work is progressing both internally and externally, enhancing the building’s energy efficiency and aesthetics. The installation of interior ceramic tiles is nearly complete, contributing to the elegant design of our spaces. We’re also excited to report that the sauna and steam room installations are substantially complete, offering our future patrons relaxation options after a good workout.

Ceiling and Flooring: Putting on the Final Touches

As the acoustical ceiling installation continues, painting crews are working hard to add vibrant colors throughout the facility. Various flooring operations—wood, VCT (Vinyl Composition Tile), and carpet—are also in full swing, with graphic painting on wood floors beginning to take shape.

Aquatics Update: Pools Progressing

In the aquatics area, the liner installation in the lap pool is nearly complete, while work progresses in the leisure pool. We’re looking forward to these vital components being finished, as they will provide wonderful recreational opportunities for everyone.

A Glimpse at the Trails Time Capsule: August 2004

Next up is September – our last month of construction before the opening on November 20th, 2004. 

Stay tuned for next month’s update in our Behind the Build series, as we continue to celebrate the incredible journey of the Trails Recreation Center!

September 2004 | Leisure pool filled with water
Behind the Build: September 2004
Behind the Build September 2004 Read More! Behind the Build: September 2004 September marks another...
September 2003 Construction Pictures: foundation forming and rebar placement
Behind the Build: September 2003
Behind the Build September 2003 Read More! Behind the Build: September 2003 Welcome back to Behind...
October 2004 | Main lobby from second floor running track
Behind the Build: October 2004
Behind the Build October 2004 Read More! Behind the Build: October 2004 October marked the official...

Leave a Reply

Your email address will not be published. Required fields are marked *

Skip to content