Search
Close this search box.

Behind the Build
Construction Timeline

Behind the Build: Construction Timeline

Initial installation of the Rip Rap along Piney Creek
August 2003
In August 2003, the Trails Recreation Center construction faced initial delays due to required bank stabilization on Piney Creek, postponed by permit and environmental conditions. Despite setbacks, foundation work, storm sewer installation, and full-scale bank stabilization launched by mid-August, setting a solid foundation for the project’s continued progress.
September 2003 Construction Pictures: foundation forming and rebar placement
September 2003
In September 2003, the Trails Recreation Center construction progressed significantly, with completed creek stabilization, finished site grading, and installation of essential underground utilities like storm sewers, water, and gas mains. Foundation walls were formed, and initial structural steel deliveries marked the start of the building’s above-ground framework, while curb and gutter installation began shaping the landscape.
October 2003 Construction Pictures: masonry screen wall foundations being poured
October 2003
In October 2003, the Trails Recreation Center project saw major advancements as bank stabilization was completed, curb and gutter installation finished, and the first asphalt layer was laid, shaping the site’s layout. This month also marked the start of structural steel erection and the initial construction of the water slide tower, signaling the transition from groundwork to vertical building.
November 2003 Construction Pictures: Structural steel erection of building
November 2003
In November 2003, the Trails Recreation Center construction advanced significantly, with nearly all excavation completed, initial asphalt layers laid, and 50% of structural steel and wood trusses erected, defining the building's shape. Key infrastructure like plumbing, electrical, and the Piney Creek bridge abutments were also completed, preparing the site for further progress toward the facility’s final structure.
December 2003 Construction Pictures: Slab grade preparation for the lower fitness floor
December 2003
In December 2003, the Trails Recreation Center construction hit major milestones, including the completion of the foundation, structural framework, and the installation of the Piney Creek bridge, making the site fully accessible. With roof decking, exterior framing, and initial HVAC, plumbing, and electrical work underway, the building began taking shape both inside and out, setting the stage for interior development in the coming year.
January 2004 Main Gym exterior steel studs and sheathing is in progress. The concrete floor slab has been poured. Overhead electrical rough is in progress
January 2004
In January 2004, construction at the Trails Recreation Center progressed rapidly, with concrete pours for interior floors and pool excavation marking significant milestones despite winter weather. Masonry work, roofing, and essential systems like ductwork and fireproofing moved forward, shaping both the building’s exterior and interior framework.
February 2004 Exterior wall mockup with human scale figures
February 2004
In February 2004, progress at the Trails Recreation Center surged ahead with masonry work, high bay lighting installations, and exciting pool preparations. The month marked key steps toward completion as walls rose, essential systems were installed, and Myrtha pool parts arrived, bringing the future aquatic center closer to life.
March 2004 View looking east at climbing wall tower
March 2004
In March 2004, the Trails Recreation Center experienced significant progress with the completion of concrete pouring for key features like the grand staircase and fitness ramps, while the Myrtha pool installation advanced with the lap pool nearly finished. Additionally, the installation of HVAC units and the near-completion of exterior prairie stonework brought the facility closer to its vision as a community hub.
April 2004 | Installation of interior steel railings in progress
April 2004
In April 2004, the Trails Recreation Center made significant strides with the installation of elegant ornamental handrails and the successful addition of skylights, bringing natural light into the facility and enhancing its overall aesthetic. The month also saw substantial progress in concrete work, roofing, and interior drywall installation, all contributing to the welcoming atmosphere that awaits future visitors.
May 2004 | Exterior synthetic stone and EFIS installation in progress fitness area
May 2004
In May 2004, the Trails Recreation Center achieved key milestones with the completion of exterior stonework and the installation of 40% of aluminum window frames, enhancing both aesthetics and natural lighting. Inside, the arrival of gym equipment and scoreboards, alongside progress on the swimming pools and climbing wall, brought the facility closer to its goal of becoming a vibrant community hub for fitness and recreation.
June 2004 | Water slide 'plunge pool' walls in progress
June 2004
In June 2004, the Trails Recreation Center saw significant advancements, including the installation of interior finishes such as cabinetry in the kitchen and locker rooms, along with progress on drywall and ceramic tiles. Additionally, the approval for the new skatepark marked an exciting development, ensuring the center will be a vibrant hub for fitness and recreation as it approaches its grand opening.
July 2004 | Reception desk millwork installation in progress
July 2004
In July 2004, the Trails Recreation Center made significant strides toward completion, with the pouring of concrete sidewalks and the installation of structural footings, walls, and columns for outdoor spaces designed for community gatherings. The installation of gym equipment and lockers progressed, while exciting developments continued at the skatepark, setting the stage for an engaging and vibrant community hub as the grand opening approaches.
August 2004 |
August 2004
 

In August 2004, the Trails Recreation Center saw significant progress with landscaping efforts, including fine grading and irrigation system installation, creating a beautiful environment around the facility. Interior finishes advanced as well, with nearly complete ceramic tile work and sauna installations, while pool liner installation was underway, all contributing to the welcoming atmosphere as the grand opening on November 20th approaches.

September 2004 | Landscaping in progress on entire site
September 2004
 

In September 2004, the Trails Recreation Center made significant strides toward completion, with exterior landscaping and site furniture installation nearing the finish line, alongside fully operational pools filled with water. Interior advancements included the installation of wood flooring in the gymnasium and fitness equipment, while skatepark construction progressed despite weather delays, setting the stage for a vibrant community hub.

October 2004 | Main lobby from second floor running track
October 2004
In May 2004, the Trails Recreation Center achieved key milestones with the completion of exterior stonework and the installation of 40% of aluminum window frames, enhancing both aesthetics and natural lighting. Inside, the arrival of gym equipment and scoreboards, alongside progress on the swimming pools and climbing wall, brought the facility closer to its goal of becoming a vibrant community hub for fitness and recreation.

Leave a Reply

Your email address will not be published. Required fields are marked *

Skip to content