Search
Close this search box.

Behind the Build

November 2003

Behind the Build: November 2003

Welcome back to Behind the Build, where we celebrate the construction of the Trails Recreation Center month by month. Remember how, in October, we saw the first parts of the structure being put into place? Well, in November 2003, the project continued to rise, taking on more of the recognizable shape we know today. From the completion of major groundwork to the beginnings of the roof, it was a month full of visible progress. Let’s dive into the details!

Excavation Milestones and Asphalt Progress

November saw the completion of nearly all the excavation work on-site, with only the two pools still left to be dug. This marked a major turning point, as it allowed for smoother movement around the site. The lower lift of asphalt was laid in the driveways and parking lots, preparing these areas for the final surface layers in the months to come. With this step, the site was becoming more accessible and functional for construction vehicles and crews.

Foundation and Framework Updates

While the foundation work for the building was nearly wrapped up, November’s real star was the continued rise of the structural steel and wood trusses. By the end of the month, 50% of the structural steel and wood truss erection was complete, giving the building a much more defined shape. Notably, the structural steel supports for the water slide were installed, hinting at the fun features that would soon become a centerpiece of the recreation center.

Rising Above: Roof Decking and Exterior Framing

The next phase of construction saw progress on the building’s exterior. The metal roof decking began taking shape, offering a first glimpse of the building’s final structure. At the same time, the exterior structural stud framing was well underway, adding definition to the building’s walls. While much of the site still resembled a skeleton of the finished facility, you could already see the framework for what would soon become the heart of the community.

Infrastructure: Plumbing and Electrical Installation

Underground work also made steady progress in November 2003, with plumbing and electrical installations in full swing. Crews were hard at work ensuring the facility would have the necessary utilities to support its future users. Though these systems remained hidden from sight, they played a crucial role in preparing the building for its eventual completion.

Piney Creek Bridge Abutments

One of the standout achievements of November was the completion of the Piney Creek bridge abutments. This important piece of infrastructure ensured safe and secure access to the recreation center from the surrounding areas. It was an essential component for connecting the facility to the local community.

What’s Next?

With November’s progress, the Trails Recreation Center was starting to take shape both inside and out. From structural steel to underground plumbing, every aspect was moving toward the grand vision of the finished facility.

Stay tuned for our next post in Behind the Build as we cover the final month of 2003 and see more of the facility rise before our eyes!

A Glimpse at the Trails Time Capsule: November 2003

September 2004 | Leisure pool filled with water
Behind the Build: September 2004
Behind the Build September 2004 Read More! Behind the Build: September 2004 September marks another...
September 2003 Construction Pictures: foundation forming and rebar placement
Behind the Build: September 2003
Behind the Build September 2003 Read More! Behind the Build: September 2003 Welcome back to Behind...
October 2004 | Main lobby from second floor running track
Behind the Build: October 2004
Behind the Build October 2004 Read More! Behind the Build: October 2004 October marked the official...

Leave a Reply

Your email address will not be published. Required fields are marked *

Skip to content