Behind the Build: October 2003
Welcome back to Behind the Build, where we continue our month-by-month celebration of the Trails Recreation Center’s 20th anniversary! Last month, we started on the groundwork. October 2003 was a transformative month as the project moved from groundwork to steel framework, marking the beginning of the center’s physical rise from the site. Let’s take a look at the exciting progress made this month.
Bank Stabilization Completed
After months of preparation and careful work along Piney Creek, the bank stabilization efforts were officially completed in October 2003. This essential step ensured the safety and stability of the surrounding land, protecting both the rec center site and the natural environment. With this major milestone behind us, the construction crew could turn their full attention to building up.
Curb, Gutter, and Asphalt—Oh My!
The site’s infrastructure continued to take shape with the completion of curb and gutter installation. Additionally, the first lift of asphalt was laid, adding yet another layer of structure to the future parking areas and pathways. Though it might seem like a small detail, these elements helped define the layout and give the site a more finished look, preparing it for the heavy equipment and workers to come.
Building Foundations Near Completion
With the foundations for the rec center nearly complete, the site was buzzing with activity. The underground building utilities were also in progress, bringing water, gas, and other essential connections to the future facility. As the concrete foundation was solidified, crews wasted no time moving forward with the next major phase of construction.
Steel and the Water Slide Tower Begin to Rise
October 2003 marked the official start of structural steel erection—a pivotal moment for any construction project. Seeing the first beams go up was a thrilling sight, signaling the transition from foundation work to vertical construction. As the steel framework rose, so did the first sections of the water slide tower. Each piece of placed steel gave everyone on-site a glimpse of what was to come.
What’s Next?
With bank stabilization and major site work behind us, October represented the start of an exciting new phase. The rec center’s framework was finally beginning to rise from the ground, and soon, the project would truly take on its form.
Stay tuned for next month’s edition of Behind the Build, where we’ll watch the steel framework continue to rise and dive deeper into the progress that November brings!